Control Room Console Factory Acceptance Test: What to Check Before Shipment
A factory acceptance test (FAT) checks the assembled control room consoles against approved drawings and the agreed supply scope before they are packed. A practical console FAT covers module fit, equipment mounting, cable routing, service access, specified functions and packing identification. The result should be a signed inspection record that tells the project team what passed, what needs correction and what must be verified at site.

Start with the approved drawing and one representative workstation
Bring the latest approved layout, console drawings, equipment list and supply schedule to the inspection. Match the drawing revision and module IDs to the items on the factory floor. Ask the supplier to identify any equipment or services that will only be available at site.
For a room with repeated stations, agree in advance which checks will be repeated on every unit and which will be sampled. Include any configuration that differs from the typical workstation, such as a corner return, a supervisor position or a sit-stand module with a different equipment layout.
ISO 11064-4 provides an ergonomic reference for control-centre workstation layout and dimensions. Use the approved project specification and drawings to define the acceptance limits for your order. ISO 11064-4 scope
Pre-shipment console FAT checklist
Check | What to verify at the factory | What to record |
Module fit and dimensions | Assemble a representative row or corner. Check critical dimensions, module joints and end panels against the approved layout. | Drawing revision, actual measurements and a photo showing module IDs. |
Display and equipment fit | Fit the specified monitor arm and equipment, or use an agreed mock-up. Check mounting interfaces and connector clearance. | Equipment or mock-up used, mounting location and any limits of the test. |
Cable routing | Route representative cables from the equipment bay to the operator position. For adjustable consoles, check the route throughout the agreed travel range. | Entry and exit points, any pinching or snagging, and any route that needs correction. |
Service access | Open the relevant panels and demonstrate how a technician reaches and removes one agreed item of equipment. | Access side, tools needed and any component that has to be moved first. |
Specified functions | Demonstrate the functions included in the order, such as height adjustment, and check the operating range against the approved specification. | Unit ID, test condition, measured result and pass or fail status. |
Packing and labels | Match each shipping label to its module ID, drawing and packing list. Confirm hardware and spares are identified. | Package IDs, contents, loose hardware and packing photos. |
A check worth doing live: Ask the supplier to fit a representative device in the equipment bay, connect its cables, close the panel and then show how the device will be removed for service. A bay can look spacious while empty. The removal demonstration reveals whether connectors, brackets or nearby modules get in the way.

Record exceptions before releasing the shipment
For every open item, write down the module ID, the drawing or specification reference, the issue, the person responsible and the evidence needed to close it. A useful entry is specific enough for someone who missed the inspection to verify the correction.
Example inspection entry: C-03 | Drawing Rev. C | Cable contacts the panel during closing | Reposition the retaining clip | Recheck through full panel movement and attach a photo before release.
If a check depends on actual room dimensions, the video wall, building services or customer-supplied equipment, assign it to site acceptance and name the person responsible. Keep that handover item visible in the signed record.
Frequently asked questions
Does a console FAT replace site acceptance testing?
No. FAT checks the agreed factory scope before shipment. Site acceptance verifies installation, actual room clearances and interfaces with building services and equipment.
Can a console FAT be performed remotely?
Yes, where the contract allows it. Ask for a live walkthrough, visible measurements, photos tied to console IDs and a signed punch list with owners and due dates.
Planning a control room console project? Send Kesino your room plan, operator count, monitor sizes and equipment list. Include any delivery or installation constraints so we can discuss the console configuration and which checks should be agreed before production. Request a console layout review and quote